Project termination (or close-out) is the last stage of managing the project, and occurs after the implementation phase has ended. Acceptance testing has been carried out, and the project deliverables have been handed over to the client. The project team has been disbanded and unused resources have been disposed of as appropriate. All outstanding bills have been passed for payment, and the final invoices for work carried out have been issued. The main purpose of the close-out stage is to evaluate how well you performed, and to learn lessons for the future. A final project status report is prepared that should contain a summary of changes to the project scope (if any), and show how actual completion dates for project milestones and costs accrued compare with the final version of the project schedule and budget. All significant variances from the project baseline should be explained here. A review is then undertaken with the client and other project stakeholders, during which the project outcomes are evaluated against the project's stated aims and objectives. The results of the review are recorded in a close-out report. The questions the stakeholders should be asked will vary depending on the nature of the project, but will normally include questions such as:
Projects fail for many reasons, some of which are outside the control of the project manager. External factors that can affect the outcome include a changing commercial environment, lack of support from senior management (including the provision of adequate resources), or lack of co-operation from the project client. Internal factors include inadequate expertise within the project team, a lack of planning and management, poorly defined project objectives, and a failure to communicate effectively. However, despite the fact that a project may not have fulfilled the expectations of its stakeholders, future projects can benefit from the lessons learned from a post-project appraisal process. It is important to learn lessons from successful aspects of the project as well as from mistakes. In that way, not only can the same mistakes be avoided in future, but good practice can be implemented in future projects. The close-out report will be the final report for the project. It will include an executive summary, the final status report, and an analysis of lessons learned that includes recommendations for improvements to be implemented in the handling of future projects. The close-out report will be made available to future project managers so that the lessons learned and the recommendations that are derived from them can be utilised. The project documentation itself will also be archived for future reference, and if it contains accurate information that has been kept up to date throughout the project it will provide a valuable source of historical data. When evaluating problems that have occurred, it is important to identify the root cause of the problem and come up with strategies for ensuring that it does not occur in future. The avoidance of certain types of problem cannot always be guaranteed (changes in scope will often occur, for example, but they can rarely be predicted). Even so, it may be possible to identify a means of detecting problems earlier in the project management process so that the negative consequences can be minimised. The importance of the availability of up to date, complete and accurate project data to the close-out process cannot be overstated. The analysis of problems and the derivation of solutions to those problems (as well as the ability to recognise and document good practice) will only be meaningful if based on a full and accurate record of what occurred during the course of the project. The memories that individual project team members and other stakeholders have of events that occurred will be distorted by time and personal bias, and therefore cannot be relied upon. It is also to some extent unfair to ask project team members to submit statements that appear critical of colleagues, or show themselves in a bad light, particularly if such statements would be made in the context of a project team de-briefing and could possibly cause some embarrassment. The idea is to highlight problems and suggest solutions, rather than to apportion blame. The project manager may well be called upon to assess and report upon the performance of individual project team members, but this assessment will usually take the form of a confidential written report that is seen only by the line manager of the individual concerned. If the project has been a success, there will be cause for some kind of celebration. This could take many forms, but represents an opportunity to thank the project team for a job well done, and to offer then a sense of closure. Even if the project has not been a complete success, it is important to thank the members of the project team for their efforts, since they have no doubt all worked hard. Where performance merits it, either the team as a whole or individual team members should be rewarded accordingly. Appreciation for a job well done may take the form of a financial reward or something less tangible. Sometimes, for some people, a sense of being truly appreciated is just as important as money. Recognition of a valuable contribution made is often sufficient incentive to ensure that an individual’s future performance will be just as good as before, if not better.
Question Control is focused on three elements of a project. They are
Answer
Question Which of the following is the key feature of cybernetic control systems?
Answer
Question Most control systems used in project management today fall into this category of control system.
Answer
Question Because project milestones may not occur at periodic intervals, go/no-go controls should be linked to the ____________; not simply to the calendar.
Answer
Question The critical ratio control chart uses a ratio made up of two parts -- the ratio of actual progress to scheduled progress, and the
Answer
Question The two fundamental objectives of control are the regulation of results and the
Answer
Question The __________ process controls the project at various points in the life cycle to make sure that the project remains on course. This is opposed to waiting until the project is completed and then finding out it doesn't meet the objectives of the organization
Answer
Question The ___________ controls take the form of testing to see if some specific precondition has been met.
Answer
Question ______________ are directed towards improving chances for future projects to meet their goals.
Answer
Question ___________ controls are usually viewed as helpful rather than as a source of unwelcome pressure if the controlees perceive themselves as able to perform inside the prescribed limits.
Answer
Question Change control systems, in some industries, are part of a firm's
Answer
Question A majority of uncertainty has its source in systems that lie outside the project, in its
Answer
Question The _____________ is calculated as (actual progress/scheduled progress) x (budgeted cost/actual cost)
Answer
Question Scope creep can be caused by the
Answer
Question _______________ is a management approach that may be used to make comparisons to "best in class" practices across organizations
Answer
Question Thamhain (2013) found that ___________ was/were not only the most frequent risk class but also had the most impact on project performance.
Answer
Question A(n) _______________ is a monitoring system that forewarns the project manager if trouble arises.
Answer
Question ______________ are seen as much the same as a report card.
Answer
Question The cybernetic control system that acts to reduce deviations from standard is called a
Answer
Question 20. For all but __________changes, a risk identification and analysis should be performed.
Answer
Question The project audit covers
Answer
Question The dimension of project success includes the obvious factors of meeting the project's technical and operational specifications. It also includes factors relating to loyalty and repurchase.
Answer
Question The __________ dimension of project success includes factors relating to opening a new market, developing a new line of products or services. Alternatively, if an internal project, success factors include developing new technologies, skills, or competencies
Answer
Question Identification of the direct goals of a project requires
Answer
Question Two of the most common limits on the depth of an investigation and level of detail presented in an audit report are
Answer
Question The accumulation, storage, and maintenance of auditable data are important cost elements. Such storage may be critically important in meeting the legal test of
Answer
Question Audits done early in the project lifecycle are often focused on
Answer
Question For audits made late in the project's life, ____________ are major matters of interest
Answer
Question In the audit report, negative comments about individuals or groups associated with the project should be
Answer
Question An evaluation of the likely outcomes of a policy and their probability of occurrence, usually conducted to compare two or more scenarios or policies is known as
Answer
Question ___________ is defined as a standard for performance, commonly established early on for later comparisons
Answer
Question ____________tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.
Answer
Question The most immediate dimension of project success is the project's _____________ in meeting both budget and schedule
Answer
Question A typical detailed audit is conducted when _______________ is required
Answer
Question The stated project objectives, including customer satisfaction, are part of the project's ________ goals
Answer
Question The ____________ section of an audit report contains a description of the project to provide a framework of understanding for the reader. Project objectives are clearly delineated.
Answer
Question In the current status section of an audit report, the subheading labeled ____________ will compare the work completed with the resources expended.
Answer
Question The _______________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach, schedule, or budget that should be made in the remaining tasks
Answer
Question In the Future Project Status section of the audit report, no assumptions should be made about _________ that are still under investigation at the time of the audit.
Answer
Question Contact between the a/e team and the _______________ are not made without clearance from senior management
Answer
Question The termination stage of the project rarely has much impact on
Answer
Question When a decision is made to terminate a project by extinction, the most noticeable event is that
Answer
Question In termination by addition, project assets are
Answer
Question When an in-house project is a major success and it is terminated by institutionalizing it as a formal part of the parent organization; this is termination by
Answer
Question According to research by Pinto, the two most important critical success factors are
Answer
Question The fundamental purpose of the final project report is to
Answer
Question A common mistake in project management is to appoint as project manager an individual with excellent ________ skills but weak ___________ skills.
Answer
Question Most studies have shown that the factors associated with project success or failure
Answer
Question The project performance section of the final report
Answer
Question The techniques of project management section of the final report
Answer
Question The special case of termination by extinction wherein the project experiences a sudden demise even though it was lacking obvious signals that death was imminent is known as
Answer
Question Special ___________ managers are sometimes useful in completing the long and involved process of shutting down the project.
Answer
Question The ___________ section of the final project report is a comparison of what the project achieved with what the project tried to achieve.
Answer
Question Cutting a project's budget sufficiently to stop progress without actually killing the project is referred to as
Answer
Question The primary criterion for project _____________ is whether or not the organization is willing to invest the estimated time and cost required to complete the project, given the project's current status and current expected outcome.
Answer
Question Bringing the project into the organization as a separate, ongoing entity is called
Answer
Question According to the text, a _________ cost is generally not relevant to current investment decisions. Rather, decision-makers should focus on the time and cost required to complete the project.
Answer
Question If a project is a major success and it is terminated, by institutionalizing it as a formal part of the parent organization, this is an example of termination by
Answer
Question Which of the following is not a common task for a termination manager?
Answer
Question In termination by integration, project assets are
Answer
|